One delivery promise across three plants.

Three plants, nine lines and more than 100 SKUs. Checking orders, capacity and material together gave planning and each plant the same answer before a delivery was promised.

Download case study PDF
₹509 crore

Year-on-year revenue increase

Accounts revenue; separate from planning impact

63% → 78%

On time in full

15 percentage points

45 → 18 min

Changeover time

One-year planning comparison

₹509 crore is the year-on-year increase in standalone accounts revenue. It is business context, not revenue attributed solely to Neuron. Delivery and changeover figures are from the planning comparison.

01 / THE CHALLENGE

Three spreadsheets gave three answers.

Avanti Frozen processes 2,500 metric tonnes per month across three plants and nine lines. A planner spent about five hours each week reconciling three spreadsheets. An order could appear possible at one plant and not at another; one in four orders sat in that gap.

02 / WHAT CHANGED

Checking the promise before making it.

Neuron checked the order, the line and the material across the plants. Planning and each plant could see the same answer before committing to a delivery. Changeover requirements were included in that plan.

This replaced the planner’s separate reconciliation with a shared feasibility check across the network.

03 / THE IMPACT

Better delivery performance across the network.

On-time-in-full delivery moved from 63% to 78%, a gain of 15 percentage points. Changeover time moved from 45 minutes to 18 minutes; the planning account reports the five-hour weekly check becoming instant.

Separately, the standalone accounts report revenue rising from ₹1,180.27 crore to ₹1,689.46 crore year on year—about ₹509 crore. This is the accounts result for the three plants, distinct from the operational planning measures.

04 / THE FIGURES

The comparison behind the result.

Avanti Frozen · Design partner — reported comparison
Planning measureBeforeAfter
On time in full63%78%
Planning check5 hours/weekInstant
Changeover45 min18 min

Three plants, nine lines, one-year planning comparison. Year-on-year revenue is from standalone accounts; it is not presented as revenue caused solely by the planning change.

Read the full case study PDF
PUT CONTEXT TO WORK

Start with the question
your team needs to answer.

Talk to us Try Neuron free